POWER ADVISORIES
Ang aton mga substations nga na energize ang nag-off line sa liwat subong alas 9:08 a.m. bangud sang pag-tripping sang planta sang PEDC nga nagdulot sang unstable nga supply sang kuryente sa bug-os nga Panay power grid. Sa subong nga ti-on ang mga energized nga mga feeders amo ang mga masunod: Sara Substation- Feeder 4 Read more
ari ang eksplinasyon nahangungod sa pagpatigayon sang MLD sang aton nga Coverage Area. INDI ini kontrolado sang ILECO III bangud kulang ang supply sang kuryente nga ginahatag sang generation apang ang demand nga ginakinahanglan sang aton miyembro-konsumidor ang masobra sa available nga capasidad sang planta. Madamo gid nga salamat sa inyo nga paghangop. Read more
“Visayas grid status, 29 April 2023: At 8:54 AM, NGCP monitored a disturbance. Multiple power plants in Panay disengaged from the transmission system. Parts of the franchise areas of AKELCO , CAPELCO, ANTECO, MORE Power, ILECO I, ILECO II, and ILECO III lost power. NGCP is investigating the root cause of the system disturbance and Read more
Ang aton mga substations nga na energize ang nag-off line sa liwat subong alas 9:08 a.m. bangud sang pag-tripping sang planta sang PEDC nga nagdulot sang unstable nga supply sang kuryente sa bug-os nga Panay power grid. Sara Substation- De-Energized Ajuy Substation – De-Energized Banate Substation -De-Energized Balasan Substation -De-Energized Daan Banwa Substation – Not Read more
Nag abiso ang PEDC nga nagtripped and ila nga unit 1 & 3 kag yara na sa under investigation ang status sang ila nga mga planta alas 2:39 kagina sang kaagahon. Nag paguwa naman sa liwat ang PEDC sang update alas 6:00 kagina sang aga nga nasynchronize na nila liwat ang Unit 1 nila ng Read more
SARA SUBSTATION BANATE SUBSTATION DAAN BANWA AJUY SUBSTATION NATIVIDAD SUBSTATION was de-energized due to NGCP shutdown. ILECO III Technical Team is still closely coordinating with National Grid Corporation of the Philippines (NGCP) and power suppliers for total power restoration of franchise coverage. Power restoration to affected areas is not yet determined. We apologized for the Read more
Power were restored in: ANILAOBANATEBAROTAC VIEJOSAN RAFAEL Additional power restored in: SAN DIONISIOLEMERY PORTION OF SARA While Daan Banwa Substation Feeder 1 was de-energized at around 11:19 PM due to Manual Load Dropping. Power restoration to affected areas is not yet determined. ILECO III Technical Team is still closely coordinating with National Grid Corporation of Read more
Date: April 28, 2023 (Friday) Time of interruption: 11:19 PM Affected areas: Feeder 1-Daan Banwa Substation TIME OF POWER RESTORATION: NOT YET DETERMINED For your information. Read more
Power were restored in: ANILAOBANATEBAROTAC VIEJO PORTION OF ESTANCIACARLES (ISLAND BARANGAYS ONLY)PORTION OF BALASAN Additional power restored in SAN RAFAEL. Power restoration to affected areas is not yet determined. ILECO III Technical Team is still closely coordinating with National Grid Corporation of the Philippines (NGCP) and power suppliers for total power restoration of franchise coverage. Read more
Power were restored in ANILAO, BANATE AND PORTION OF BAROTAC VIEJO. Additional power restored in PORTION OF ESTANCIA, CARLES (ISLAND BARANGAYS ONLY) AND PORTION OF BALASAN. Power restoration to affected areas is not yet determined. ILECO III Technical Team is still closely coordinating with National Grid Corporation of the Philippines (NGCP) and power suppliers for Read more