LOOK: Preventive Maintenance Schedule of NGCP, ILECO III Technical Team conducting installation of Three (3) phase assembly fuse cut-out in Brgy. Abong, Carles today, August 6, 2023 (Sunday)
Keep safe Warriors of Light! For your information. National Electrification Administration
LOOK: Preventive Maintenance Schedule of NGCP, ILECO III Technical Team conducting replacement of steel pin and pin insulator in Brgy. Daan Banwa, Estancia today, August 6, 2023 (Sunday)
Keep safe Warriors of Light !For your information. National Electrification Administration
UNSCHEDULED POWER INTERRUPTION (AUGUST 5, 2023)
Date: August 5, 2023 (Saturday) Time of interruption: 8:43 AM Time of restoration: 9:08 AM Affected area: Tanza, Estancia Action Taken: Inspection and repaired secondary jumper cut-off We apologize for the inconvenience. For your information.
UNSCHEDULED POWER INTERRUPTION (AUGUST 5, 2023)
Date: August 5, 2023 (Saturday) Time of interruption: 7:20 AM Time of restoration: 8:10 AM Affected area: Nueva Invencion, Barotac Viejo Action Taken: Inspection and replaced damage fuse link due to animal contact We apologize for the inconvenience. For your...
LOOK: ILECO III Technical Team conducted rehab of kWhr Meter in NHA Village, Bacjawan Sur, Concepcion, Iloilo today, August 4, 2023 (Friday).
Keep safe Warriors of Light! For your information. Thank you.
UNSCHEDULED POWER INTERRUPTION (AUGUST 4, 2023)
Date: August 4, 2023 (Friday) Time of interruption: 7:33 AM Time of restoration: 10:14 AM Affected area: Binuluangan and Tabugon Island, Carles Action Taken: Inspection and replaced damage fuse link due to animal contact We apologize for the inconvenience. For your...
LOOK: ILECO III Technical Team installed private transformer in Estancia, Iloilo today, August 4, 2023 (Friday)
Keep safe Warriors of Light! For your information. Thank you.
UNSCHEDULED POWER INTERRUPTION (AUGUST 4, 2023)
Date: August 4, 2023 (Friday) Time of interruption: 7:49 AM Time of restoration: 9:10 AM Affected area: Posadas and Devera (Portion), Sara Action Taken: Inspection and replaced damage fuse link due to animal contact We apologize for the inconvenience. For your...
UNSCHEDULED POWER INTERRUPTION (AUGUST 3, 2023)
Date: August 3, 2023 (Thursday )Time of interruption: 7:54PM Time of restoration: 8:52PM Affected area: Pasig, Aposaga, Juaneza and Aguirre, Sara Action Taken: Inspection and replaced damage fuse link due to animal contact We apologize for the inconvenience. For your...
POWER ADVISORY
RESCHEDULED POWER INTERRUPTION Pahibalo sa mga katapo-konsumidores nga ang PREVENTIVE MAINTENANCE sang NATIONAL GRID CORPORATION OF THE PHILIPPINES (NGCP) sa ila Sara-Estancia Transmission Line Section sa AGOSTO 05, 2023 (SABADO) ang GIN-RESCHEDULED sa AGOSTO 06, 2023...