• UNSCHEDULED POWER INTERRUPTION (AUGUST 13, 2022)

    Date: August 13, 2022 Time of interruption: 8:04 AM Time of Restoration: 9:12 AM Reason: Due to human activity (cutting of Bamboo) made contact with our primary line. Affected Area: Loguingot Island, Estancia Activity: Inspection of line and re-fusing We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (AUGUST 13, 2022)

    Date: August 13, 2022 Time of interruption: 9:18 AM Time of restoration: 10:02 AM Affected area: Nagka, Batad Activity: Inspection of line and re-fusing We apologize for the inconvenience. For your information. Read more

  • NGCP’s UNSCHEDULED POWER INTERRUPTION (AUGUST 12, 2022)

    Date: August 12, 2022 Time of interruption: 6:29 P.M Time of restoration: 6:58 P.M. Affected areas: ANILAO, BANATE, SAN RAFAEL AND BAROTAC VIEJO Cause: NGCP Tripping of 69 KV Dingle Substation We apologize for the inconvenience. For your information. Read more

  • LOOK: ILECO III CONDUCTED ON-SITE PRE-MEMBERSHIP SEMINAR IN PUNTA, CARLES, ILOILO

    ILECO III conducted On-site Pre-Membership Seminar (PMS) participated by 56 attendees in Brgy. Punta, Carles, Iloilo on October 17, 2024 (Thursday). The said meeting was attended by Dir. Lope O. Salmorin. This activity is made possible with the support of ILECO III BODs and Management Committee headed by our General Manager, Atty. James G. Balsomo… Read more

  • LOOK: ILECO III CONDUCTED ON-SITE PRE-MEMBERSHIP SEMINAR IN LUMBIA, ESTANCIA, ILOILO

    ILECO III conducted On-site Pre-Membership Seminar (PMS) participated by 57 attendees in Brgy. Lumbia, Estancia, Iloilo on October 17, 2024 (Thursday). The said meeting was attended by Dir. Lope O. Salmorin. This activity is made possible with the support of ILECO III BODs and Management Committee headed by our General Manager, Atty. James G. Balsomo… Read more

  • LOOK: ILECO III CONDUCTED ON-SITE PRE-MEMBERSHIP SEMINAR IN BAROTAC VIEJO, ILOILO

    ILECO III conducted On-site Pre-Membership Seminar (PMS) participated by 84 attendees from barangays of La Fortuna, San Antonio and Ugasan held in Brgy. La Fortuna, Barotac Viejo, Iloilo on October 17, 2024 (Thursday). The said meeting was attended by Dir. Harry G. Tupas. This activity is made possible with the support of ILECO III BODs… Read more

  • ANO ANG RA 11552?

    An Act Extending and Enhancing the Implementation of the Lifeline Rate, Amending for the Purpose, Section 73 of Republic Act No. 9136, Otherwise known as the ‘Electric Power Industry Reform Act of 2001’ as Amended by Republic Act No. 10150 1. Ano ang Lifeline Rate kag ano ang benepisyo sa mga kwalipikado nga mga kunsomidor?… Read more

  • ITB 2407, S. 2024

    Invitation to Bid for the Supply, Delivery and Construction of Distribution Lines and Installation of Kwhr Meter, Service Drop Wires and House Wiring Materials in Five (5) Barangays (Brgy. Barangcalan, Brgy. Bito-on, Brgy. Talingting, Brgy. Tinigban, and Brgy. Punta Batuanan) in Calagnaan Island, Carles, Iloilo (Turn Key) Read more

  • ITB 2406, S. 2024

    Invitation to Bid for the Supply, Delivery and Construction of Distribution Lines and Installation of Kwhr Meter, Service Drop Wires and House Wiring Materials from Brgy. Poblacion to Brgy. Daculan, Estancia and Brgy. Manlot, Manlot Island, Carles, Iloilo(Turn Key) Read more

  • ITB 2405, S. 2024

    Invitation to Bid for the Design, Supply, Delivery, Installation, Testing and Commissioning of Three-Phase Submarine Line Cable from Brgy. Daculan, Estancia to Brgy. Manlot, Carles, from Brgy. Manlot to Brgy. Talingting, Carles and from Brgy. Punta Batuanan to Brgy. San Fernando, Carles, Iloilo (Turn Key) Read more