• EMERGENCY POWER INTERRUPTION (AUGUST 15, 2022)

    Date: August 15, 2022 Time of interruption: 9:42 AM Time of Restoration: 3:00 PM Affected Area: Sitio Ga-on, Brgy. Bato Biasong, Ajuy Activity: Pole hauling and erection of pole replacement of damage/rotten pole We apologize for the inconvenience. For your information. P.S We are grateful to Brgy. Captain Asturias and officials of the said barangay… Read more

  • UNSCHEDULED POWER INTERRUPTION (AUGUST 18, 2022)

    Date: August 18, 2022 Time of interruption: 9:04 AM Time of Restoration: 10:10 AM Affected Area: Tabugon Island, Carles Cause of Interruption: Transient line fault Activity: Inspection of lines and replaced busted fuselink We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (AUGUST 18, 2022)

    Date: August 18, 2022 Time of interruption: 8:15 AM Time of Restoration: 9:05 AM Affected Area: Sitio Lampuyang, Sitio Danmar and Sitio Bacolod, Libertad, Banate Cause of Interruption: Line fault due to animal contact (bat) Activity: Inspection/clearing of lines and replaced busted fuselink We apologize for the inconvenience. For your information. Read more

  • LOOK: ILECO III CONDUCTED ON-SITE PRE-MEMBERSHIP SEMINAR IN SAN LUCAS, BAROTAC VIEJO, ILOILO

    ILECO III conducted On-site Pre-Membership Seminar (PMS) participated by 57 attendees from Brgy. San Lucas, Barotac Viejo, Iloilo on November 19, 2024 (Tuesday). The said meeting was attended by Dir. Harry G. Tupas. This activity is made possible with the support of ILECO III BODs and Management Committee headed by our General Manager, Atty. James… Read more

  • TO OUR VALUED MEMBER-CONSUMER-OWNERS (MCOs),

    For individual consumers, you can pay your bills to the following third party collection centers ON or BEFORE DUE DATE. Payment beyond grace period will be considered delinquent and shall incur corresponding penalty. For BAPA Members, please pay your accounts to your respective BAPAs. A FRIENDLY REMINDER FROM ILECO III! Read more

  • LOOK: ILECO III CONDUCTED ON-SITE PRE-MEMBERSHIP SEMINAR IN VISTA ALEGRE, BAROTAC VIEJO, ILOILO

    ILECO III conducted On-site Pre-Membership Seminar (PMS) participated by 33 attendees from Brgy. Vista Alegre, Barotac Viejo, Iloilo on November 15, 2024 (Friday). The said meeting was attended by Dir. Harry G. Tupas. This activity is made possible with the support of ILECO III BODs and Management Committee headed by our General Manager, Atty. James… Read more

  • LOOK: ILECO III CONDUCTED ON-SITE PRE-MEMBERSHIP SEMINAR IN JOLOG, ESTANCIA, ILOILO

    ILECO III conducted On-site Pre-Membership Seminar (PMS) participated by 29 attendees in Brgy. Jolog, Estancia, Iloilo on November 15, 2024 (Friday). The said meeting was attended by Punong Barangay Hon. Alicia Base. This activity is made possible with the support of ILECO III BODs and Management Committee headed by our General Manager, Atty. James G.… Read more

  • ITB 2209, S. 2022

    Procurement of Materials for Construction of Distribution Lines and Supply, Delivery and Installation of Kwhr Meter for Sitio Electrification Program (SEP) – Forty Four (44) Sitios Read more

  • ITB 2208, S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB 2207, S. 2022

    Re-Bidding of the Procurement of Materials and Equipment for Change Meter/Rehabilitation, Service Drop Installation, Housewiring Land and Maintenance Use Read more