• UNSCHEDULED POWER INTERRUPTION (FEBRUARY 1, 2023)

    Date: February 01, 2023 (Wednesday) Time of interruption: 2:00 PM Time of restoration: 3:10 PM Affected area: Poblacion, Anilao, Iloilo (portion) Activity: Installed correctional pole We apologize for the inconvenience. For your information. Read more

  • THERMAL SCANNING OF DISTRIBUTION LINES

    ILECO III Technical Team conducted Thermal scanning of Distribution Lines to determine hotspots of distribution lines and to reduce system loss today, January 31, 2023 (Tuesday). For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (JANUARY 31, 2023)

    Date: January 31, 2023 Time of interruption: 11:30 AM Time of restoration: 3:25 PM Affected area: Trinidad Village, Poblacion, Barotac Viejo, Iloilo Activity: Replaced rotten pole We apologize for the inconvenience. For your information. Read more

  • ILECO III OFFICES AND AREA COVERAGE

    For complaints regarding power interruptions, please call the Area Offices to report. Thank you and keep safe our beloved MCOs. Read more

  • DIIN NAGA HALIN ANG ATON KURYENTE?

    GENERATION- Ini ang ginabug-osan sang mga Independent Power Producer ukon IPPs katulad sang (SIPC, GCGI, PEDC kag GMPC) nga nagaproseso sa pag-produser sang kuryente kag diri nakakontrata ang suplay sang kuryente ni ILECO III. TRANSMISSION- Ini ang ginadumala ukon ginamintenar sang National Grid Corporation of the Philippines o (NGCP) nga gina-agyan sang kuryente halin sa… Read more

  • HAPPY BIRTHDAY VICE MAYOR GANZON!

    Happy birthday HON. MANUEL C. GANZON, Municipal Vice Mayor- Balasan, Iloilo.From ILECO III Family! Manuel Ganzon Read more

  • Happy birthday to our very own General Manager, ATTY. JAMES G. BALSOMO II!

    May your day be filled with joy, gratitude, and hope for the year ahead, and may our Almighty God continue to bless you and watch over you all the days of your life. From your ILECO III Family! Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more