• UNSCHEDULED POWER INTERRUPTION (MAY 3, 2022)

    Date: May 03, 2022 (Tuesday) Time of interruption: 12:33 PM Time of restoration: 1:15 PM Affected area: Banate and Anilao, Iloilo Cause of interruption: Line fault due to vegetation Activity: Clearing of line and replaced busted fuse link We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (MAY 2, 2022)

    Date: May 02, 2022 (Monday) Time of interruption: 4:56 PM Time of restoration: 6:10 PM Affected area: Sitio Balabag, San Fernando, Barotac Viejo, Iloilo Cause of interruption: Line fault due to vegetation We apologize for the inconvenience. For your information. Read more

  • UPDATE ON NGCP UNSCHEDULED POWER INTERRUPTION( As of 4:50 p.m.)

    Pahibalo sa mga katapo-konsumidores nga na-energize na ang tanan nga apat (4) ka substations sang ILECO III nga apektado sang UNSCHEDULED POWER INTERRUPTION sang NGCP. Sa sini nga bahin, nagbalik na ang power supply sa tanan nga siyam (9) ka banwa: AJUY, SARA, LEMERY, SAN DIONISIO, CONCEPCION, BATAD, ESTANCIA, BALASAN kag CARLES. Ang NGCP ang… Read more

  • ENERGY SAVING TIP

    Unplug devices when not in use. Read more

  • FREQUENTLY ASKED QUESTIONS

    ANO ANG DAPAT UBRAHON KUNG MAY ARA NGA POWER INTERRUPTION SA AMON LUGAR? Read more

  • SAFETY TIPS SA PANAHON SANG TAG-ULAN

    1. Patyon ang Main Switch kung nagabaha na sa inyo lugar. 2. Indi pagtandugon ang mga basa nga wirings sang kuryente. 3. Indi magsaka sa mga kahoy bangud possible nga maglatay ang boltahe sang kuryente sa mga basa nga sanga. 4. Pagkatapos mabahaan ang inyo lugar, indi anay pagbuksan ang main switch. Magtawag sang accredited… Read more

  • ENERGY SAVING TIP

    Turn off the lights when not needed. Read more

  • ITB 2209, S. 2022

    Procurement of Materials for Construction of Distribution Lines and Supply, Delivery and Installation of Kwhr Meter for Sitio Electrification Program (SEP) – Forty Four (44) Sitios Read more

  • ITB 2208, S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB 2207, S. 2022

    Re-Bidding of the Procurement of Materials and Equipment for Change Meter/Rehabilitation, Service Drop Installation, Housewiring Land and Maintenance Use Read more