• EMERGENCY POWER INTERRUPTION (NOVEMBER 1, 2022)

    Date: November 1, 2022 Time of interruption: 8:12 AM Time of Restoration: 8:42 AM Affected Area: Whole Feeder 1 of Sara Substation (Brgys of Sara and San Dionisio) Afftected Areas: Sara Substation (Feeder 1)Sara: Aldeguer and Castor (Portion)San Dionisio: Dugman, Tuble, San Nicolas, Cudionan, Had. Conchita, Sua, Tiabas, Cubay, Bagacay, Agdaliran, Borongon, Manduawak, Talo-ato, Batuan,… Read more

  • UNSCHEDULED POWER INTERRUPTION (OCTOBER 31, 2022)

    Date: October 31, 2022 Time of interruption: 8:55 PM Time of Restoration: 9:15 PM Affected Area: NHA Village, Magdalo, Banate Reason/Activity: Line fault due to damage of secondary bushing/ Inspection and repaired damaged secondary bushing. We apologize for the inconvenience. For your information. Read more

  • TROUBLESHOOTING OF FEEDER 1 LINE FAULT SUSPENSION INSULATR CENTER PHASE C8 IN DEVERA, SARA

    ILECO III Technical personnel troubleshoot Feeder 1 line fault suspension insulator center phase C8 at Brgy. Devera, Sara, today October 31, 2022 (Monday). Keep safe Warriors of Light For your information. Read more

  • ENERGY SAVING TIP

    Unplug devices when not in use. Read more

  • FREQUENTLY ASKED QUESTIONS

    ANO ANG DAPAT UBRAHON KUNG MAY ARA NGA POWER INTERRUPTION SA AMON LUGAR? Read more

  • SAFETY TIPS SA PANAHON SANG TAG-ULAN

    1. Patyon ang Main Switch kung nagabaha na sa inyo lugar. 2. Indi pagtandugon ang mga basa nga wirings sang kuryente. 3. Indi magsaka sa mga kahoy bangud possible nga maglatay ang boltahe sang kuryente sa mga basa nga sanga. 4. Pagkatapos mabahaan ang inyo lugar, indi anay pagbuksan ang main switch. Magtawag sang accredited… Read more

  • ENERGY SAVING TIP

    Turn off the lights when not needed. Read more

  • ITB 2209, S. 2022

    Procurement of Materials for Construction of Distribution Lines and Supply, Delivery and Installation of Kwhr Meter for Sitio Electrification Program (SEP) – Forty Four (44) Sitios Read more

  • ITB 2208, S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB 2207, S. 2022

    Re-Bidding of the Procurement of Materials and Equipment for Change Meter/Rehabilitation, Service Drop Installation, Housewiring Land and Maintenance Use Read more