• Statement of NGCP regarding the situation of Power Supply in the Panay Grid

    https://web.facebook.com/NGCPph/posts/pfbid03884fTS6UFPzAQyrVSGUtukDQDXxQTRqwDQqLW6YHTLdQQeuj311E8uus4Zvjjcril Read more

  • POWER ADVISORY UPDATE as of 11:05 a.m., April 29, 2023

    Ang aton mga substations nga na energize ang nag-off line sa liwat subong alas 9:08 a.m. bangud sang pag-tripping sang planta sang PEDC nga nagdulot sang unstable nga supply sang kuryente sa bug-os nga Panay power grid. Sa subong nga ti-on ang mga energized nga mga feeders amo ang mga masunod: Sara Substation- Feeder 4 Read more

  • Ano ang Manual Load Dropping sang NGCP?

    ari ang eksplinasyon nahangungod sa pagpatigayon sang MLD sang aton nga Coverage Area. INDI ini kontrolado sang ILECO III bangud kulang ang supply sang kuryente nga ginahatag sang generation apang ang demand nga ginakinahanglan sang aton miyembro-konsumidor ang masobra sa available nga capasidad sang planta. Madamo gid nga salamat sa inyo nga paghangop. Read more

  • LOOK: ILECO III CONDUCTED ON-SITE PRE-MEMBERSHIP SEMINAR IN IMBAULAN, LEMERY, ILOILO

    ILECO III conducted On-site Pre-Membership Seminar (PMS) participated by 49 attendees in Brgy. Imbaulan, Lemery, Iloilo on October 28, 2024 (Monday). The said meeting was attended by barangay officials heade by Punong Barangay Hon. Rabie Villegas. This activity is made possible with the support of ILECO III BODs and Management Committee headed by our General Read more

  • LOOK: ILECO III CONDUCTED ON-SITE PRE-MEMBERSHIP SEMINAR IN BINON-AN, BATAD, ILOILO

    ILECO III conducted On-site Pre-Membership Seminar (PMS) participated by 51 attendees in Brgy. Binon-an, Batad, loilo on October 28, 2024 (Monday). The said meeting was attended by Dir. Lope, Salmorin. This activity is made possible with the support of ILECO III BODs and Management Committee headed by our General Manager, Atty. James G. Balsomo II. Read more

  • HOW TO USE PayMaya APP TO PAY ILECO III BILLS

    IMPORTANT REMINDERS 1. Payments thru PayMaya are only accepted ON or BEFORE due date indicated on the right portion of your statement of account. 2. Check all the provided details prior to payment of bills. 3. Past due bills and partial payments will not be posted. Please settle your accounts to the nearest ILECO III Read more

  • ENERGY CONSERVATION TIPS

    Ka-MCO! Looking for ways to save energy and money at home? Take a look at these Energy Conservation Tips we have put together, they could help you in reducing your monthly bills. Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more