• MAY SCHEDULED PREVENTIVE MAINTENANCE KAG LOAD TRANSFER ANG NGCP SA HULYO 15, 2023

    Pahibalo sa mga katapo-konsumidores nga may patigayunon nga SCHEDULED PREVENTIVE MAINTENANCE kag LOAD TRANSFER ang NATIONAL GRID CORPORATION OF THE PHILIPPINES (NGCP) sa ila 69 kV Sara-Estancia Transmission Line Section sa HULYO 15, 2023 (SABADO). Ang oras kag apektado nga lugar sang sini power interruption amo ang masunod: 5:00 AM- 6:00 PM (13 ka oras… Read more

  • NGCP’s UNSCHEDULED POWER INTERRUPTION

    DATE: July 06, 2023 (Thursday) Time of interruption:Ajuy S/s: 9:00PMSara S/s: 9:00 PMPani-an S/s: 9:01 PMDaan Banwa S/s: 9:00 PM Estimated Time of power restoration: Sara S/s: 9:10 PMAjuy S/s: 9:08 PMPani-an S/s: 9:13 PMDaan Banwa S/s: 9:15 PM Affected areas: Whole coverage of ILECO III Cause of interruption: UNDER INVESTIGATION Our technical team is… Read more

  • NGCP’s UNSCHEDULED POWER INTERRUPTION (UPDATE)

    DATE: July 05, 2023 (Wednesday) Time of interruption:Barotac Viejo S/s: 8:50 PMBanate S/s: 8:50 PM Estimated Time of power restoration: Barotac Viejo S/s : 9:05 PMBanate S/s: 9:06 PM Affected areas: Anilao, Banate, Barotac Viejo and San Rafael Cause of interruption: UNDER INVESTIGATION Our technical team is closely coordinating with NGCP regarding the cause of… Read more

  • ILECO III ENERGY SAVING TIPS

    1. Pag-kontrol sang konsumo sang kuryente.2. Pag-gamit sang highly resistive appliances sa tion sang off-peak (kung sa diin barato ang kuryente) ka-angay sang oven, heater, plantsa kag toasters. Likawan ang pag-gamit sang sini nga mga appliances kung peak hours humalin 6:00 PM tubtob 10:00 PM.3. Patyon ang suga sa kwarto kung wala sang tawo.4. Pagsiguro… Read more

  • ONGOING BASIC LINEMEN TRAINING COURSE HELD AT ILECO III (WEEK 3)

    The start of the actual preparations and exercises on the Basic Linemen Training Course (Week 3) were the following: 1. Pole hauling2. Hole digging3. Grounding4. Pole erection5. Guying6. Anchoring7. Pole climbing exercises8. Pole dressing9. Stringing10. Tensioning, Armouring, Tying Activities mentioned above were just the first part of the rigorous trainings of the trainees to equip… Read more

  • PLEASE INPUT THE EXACT BILL AMOUNT WHEN USING GCASH, PAYMAYA AND OTHER DIGITAL PLATFORM FOR BILLS PAYMENT

    To all Member-Consumer-Owners who pay with GCash, PayMaya and other digital platform for bills payment, please input the exact bill amount indicated in your billing statement on or before the due date. A friendly reminder from your ILECO IIIĀ  Read more

  • ONGOING BASIC LINEMEN TRAINING COURSE HELD AT ILECO III

    The start of the actual preparations and exercises on the Basic Linemen Training Course (Week 2) were the following: 1. Pole hauling2. Hole digging3. Grounding4. Pole erection5. Guying6. Anchoring7. Pole climbing exercises8. Pole dressing9. Stringing10. Tensioning, Armouring, Tying Supervising these activities are the trainers from SURSECO-1 along with the observer Engineers who are from the… Read more

  • ITB 2209, S. 2022

    Procurement of Materials for Construction of Distribution Lines and Supply, Delivery and Installation of Kwhr Meter for Sitio Electrification Program (SEP) – Forty Four (44) Sitios Read more

  • ITB 2208, S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB 2207, S. 2022

    Re-Bidding of the Procurement of Materials and Equipment for Change Meter/Rehabilitation, Service Drop Installation, Housewiring Land and Maintenance Use Read more