• UNSCHEDULED POWER INTERRUPTION (OCTOBER 11, 2022)

    Date: October 11, 2022 Time of interruption: 11:55 AM Time of Restoration: 12:05 PM Affected Area: Feeder 3 (Municipality of Batad) Reason/Activity: Vegetation contact with primary line @ Brgy. Lumbia, Estancia. Inspection/clearing of lines and replaced fuse link We apologize for the inconvenience. For your information. Read more

  • SCHEDULED POWER INTERRUPTION SA OKTUBRE 13 KAG 17, 2022

    Pahibalo sa mga katapo-konsumidores nga may SCHEDULED POWER INTERRUPTION ang ILECO III para sa pag-construct sang Single Phase Line. Ang petsa, oras kag lugar nga apektado sang sini nga power interruption sa banwa sang Estancia amo ang masunod: OKTUBRE 13, 2022 (HUWEBES)8:00 AM- 5:00 PM(9 ka oras ang kalawigon) OKTUBRE 17, 2022 (LUNES)8:00 AM- 1:00… Read more

  • CHANGE METER OF BIG LOAD CONSUMERS IN POBLACION, CONCEPCION

    ILECO III Technical personnel conducted change meter of the following big load consumers 1. Wet and Semi Wet Market 2. Concepcion Municipal Hall Gym at Poblacion, Concepcion today, October 10, 2022 (Monday). Keep safe Warriors of Light For your information. Read more

  • ILECO III OFFICES AND AREA COVERAGE

    For complaints regarding power interruptions, please call the Area Offices to report. Thank you and keep safe our beloved MCOs. Read more

  • BEAT THE HEAT!

    A friendly reminders from ILECO III. Keep safe everyone. Read more

  • ANTI-OBSTRUCTION OF POWER LINES ACT(REPUBLIC ACT 11361)

    ‘An Act Ensuring the Continuous and Uninterrupted Transmission and Distribution of Electricity and Protection of the Integrity and Reliability of Power Lines, and Providing Penalties for Violations Thereof.’ Ginadumili-an ang mga masunod: 1. Pagtanom sang maskin ano nga sahi sang matag-as ukon naga-taas nga mga tanom ukon kahoy sa idalom sang distribution lines. 2. Pagpatindog… Read more

  • ANO ANG DAPAT UBRAHON KUNG SALA ANG SPELLING SANG NGALAN SA BILL?

    Magkadto lamang sa Area Offices sang ILECO III kag magdala sang imo nga Identification Card nga may correct spelling sang imo pangalan:SARA AREA OFFICE- Brgy. Preciosa, SaraPANI-AN AREA OFFICE- Brgy. Pani-an, BalasanNATIVIDAD AREA OFFICE- Brgy. Natividad, Barotac Viejo Madamo gid nga salamat. Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more