• UNSCHEDULED POWER INTERRUPTION (APRIL 20, 2022)

    Date: April 20, 2022 (Wednesday) Time of interruption: 7:45 PM Time of restoration: 8:27 PM Affected area: Sitio Ilaya, San Roque, Barotac Viejo, Iloilo Cause of interruption: Line fault due to animal contact We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (APRIL 20, 2022)

    Date: April 20, 2022 (Wednesday) Time of interruption: 7:28 PM Time of restoration: 8:00 PM Affected area: San Antonio, Barotac Viejo, Iloilo Activity: Replaced burned suspension of tapping pole We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (APRIL 20, 2022)

    Date: April 20, 2022 (Wednesday) Time of interruption: 8:13 PM Time of restoration: 8:59 PM Affected area: NHA Village, Calapdan, Estancia, Iloilo Cause of interruption: Line fault due to animal contact We apologize for the inconvenience. For your information. Read more

  • SCHEDULE OF DUE DATES AND DISCONNECTION FOR THE MONTH OF APRIL 2025.

    For your information. Read more

  • Aton hibalu-on ang Power Bill kag Rate Composition

    Ka MCO! Aton hibalu-on ang Power Bill kag Rate Composition nga aton makita sa aton Power Bill kada bulan. Diin bala naga-kadto ang aton ginabayaran sa aton kuryente? Matuod gid man bala ang tsismis nga ang isa ka Electric Cooperative ang nagapa-gusto lang sa pag-pasaka sang kuryente? Diri naton mahibaluan kung fixed bala ang Distribution,… Read more

  • PUBLIC ADVISORY HOLIDAY NOTICE

    LABOR DAY – MAY 1, 2025 (THURSDAY) MAIN OFFICE AND AREA OFFICES – CLOSED ASSIGNED MAINTENANCE CREW ARE AVAILABLE AT AREA OFFICES TO ADDRESS YOUR CONCERNS/ COMPLAINTS. REGULAR OFFICE HOUR WILL RESUME ON MAY 2, 2025 (FRIDAY) MADAMO GID NGA SALAMAT SA INYO PAGHANGUP. Read more

  • DIIN NAGA HALIN ANG ATON KURYENTE?

    GENERATION – Ini ang ginabug-osan sang mga Independent Power Producer ukon IPPs katulad sang (SIPC, GCGI, PEDC kag GMPC) nga nagaproseso sa pag-produser sang kuryente kag diri nakakontrata ang suplay sang kuryente ni ILECO III. TRANSMISSION – Ini ang ginadumala ukon ginamintenar sang National Grid Corporation of the Philippines o (NGCP) nga gina-agyan sang kuryente… Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more