• UNSCHEDULED POWER INTERRUPTION (OCTOBER 28, 2022)

    Date: October 28, 2022 Time of interruption: 6:13 PM Time of Restoration: 7:15 PM Affected Area: Balantian, Balasan Reason/Activity: Line fault due to heavy rain and lightning surge/ Inspection of line and replaced busted fuse link. We apologize for the inconvenience. For your information. (Photo is pixelated and distorted due to heavy rain) Read more

  • UNSCHEDULED POWER INTERRUPTION (OCTOBER 28, 2022)

    Date: October 28, 2022 Time of interruption: 5:24 PM Time of Restoration: 6:48 PM Affected Area: Lawis, Balasan Reason/Activity: Line fault due to secondary jumper cut-off/ Repair secondary jumper cut-off and re-fusing We apologize for the inconvenience. For your information. (Photo is pixelated and distorted due to heavy rain) Read more

  • REPAIR OF SECONDARY JUMPER OF TRANSFORMER LOOSE CONNECTION IN BOTONON, ESTANCIA

    ILECO III Technical personnel repaired the secondary jumper of the transformer loose connection at Brgy. Botongon, Estancia today, October 28, 2022 (Friday). Keep safe Warriors of Light For your information. Read more

  • PROMPT PAYING MCOs

    Thank you to our beloved Member-Consumer-Owners (MCOs) for paying your bills promptly. Keep safe always. *Masks were removed for documentation purposes only. #1ECMCOMovement#ParaSaOneECMCOMovement#ILECO3ServiceBeyondElectricity Read more

  • PANTAWID LIWANAG PROGRAM PHASE 5 GIN PATIGAYON SANG ILECO III SA BRGY. ASLUMAN, CARLES, ILOILO

    Sa ika-lima (5) ka beses, nangin madinalag-on liwat ang ginhiwat nga Pantawid Liwanag Program (PLP) cash assistance sa idalum sang programa nga Assistance for Indigents in Crisis Situation ukon (AICS) sang Department of Social Welfare and Development sang Hunyo 03, 2022 (Biyernes). Ang funding sa sini nga programa natigayon sa pagpanikasog man sang aton APEC… Read more

  • ANTI-PILFERAGE ACT (RA 7832)

    A Friendly Reminder from ILECO III Read more

  • ANO ANG MANUAL LOAD DROPPING O MLD ?

    Ini ang proseso nga kung sa diin gina-buhinan ang power load sa grid bangud sa kakulangan sang supply sang kuryente nga masami matabo kung may mga naguba nga planta kadungan sang pag-taas sang supply sang pag-gamit sang kuryente. Bangud diri, ginapatigayon ang MLD pina-agi sa “Rotational Brownout” sa nagaka-igo nga oras sa nasakupan nga lugar… Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more