• NGCP UNSCHEDULED POWER INTERRUPTION (NOVEMBER 6, 2023)

    Date: November 6, 2023 (Monday)Time of interruption: 1:49 PMTime of restoration: Undetermined Affected areas: Municipality of Ajuy, Concepcion, Sara, Lemery, San Dionisio, Batad, Balasan, Estancia and Carles Cause of interruption: Vegetation on 69kV Sara-Balasan NGCP Transmission Line at Sitio Virgin Island, Antonio Yusay, Sara Maintenance Team is closely coordinating with NGCP regarding the true cause… Read more

  • UNSCHEDULED POWER INTERRUPTION UPDATE (NOVEMBER 4, 2023)

    Date: November 4, 2023 (Saturday) Time of interruption: 5:54 PM Time of restoration: 9:10 PM Affected areas: Feeder 1 of Sara S/s *Municipality of San Dionisio*Portion of Municipality of Sara*Brgy. Aglosong and Bacjawan Norte (Portion), Concepcion Cause of interruption: Cut-off primary line in Brgy. Castor, Sara due to severe gustiness of wind and heavy rain… Read more

  • UNSCHEDULED POWER INTERRUPTION (NOVEMBER 4, 2023)

    Date: November 4, 2023 (Saturday)Time of interruption: 5:54 PMEstimated time of restoration: Not yet determined Affected areas: Feeder 1 of Sara S/s *Municipality of San Dionisio*Portion of Municipality of Sara*Brgy. Aglosong and Bacjawan Norte (Portion), Concepcion Cause of interruption: Cut-off primary line in Brgy. Castor, Sara due to severe gustiness of wind and heavy rain… Read more

  • PANTAWID LIWANAG PROGRAM PHASE 5 GIN PATIGAYON SANG ILECO III SA BRGY. ASLUMAN, CARLES, ILOILO

    Sa ika-lima (5) ka beses, nangin madinalag-on liwat ang ginhiwat nga Pantawid Liwanag Program (PLP) cash assistance sa idalum sang programa nga Assistance for Indigents in Crisis Situation ukon (AICS) sang Department of Social Welfare and Development sang Hunyo 03, 2022 (Biyernes). Ang funding sa sini nga programa natigayon sa pagpanikasog man sang aton APEC… Read more

  • ANTI-PILFERAGE ACT (RA 7832)

    A Friendly Reminder from ILECO III Read more

  • ANO ANG MANUAL LOAD DROPPING O MLD ?

    Ini ang proseso nga kung sa diin gina-buhinan ang power load sa grid bangud sa kakulangan sang supply sang kuryente nga masami matabo kung may mga naguba nga planta kadungan sang pag-taas sang supply sang pag-gamit sang kuryente. Bangud diri, ginapatigayon ang MLD pina-agi sa “Rotational Brownout” sa nagaka-igo nga oras sa nasakupan nga lugar… Read more

  • PANTAWID LIWANAG PROGRAM PHASE 5 GIN PATIGAYON SANG ILECO III SA 2 KA BARANGAY SA ILA AREA COVERAGE

    Sa ika-lima (5) ka beses, nangin madinalag-on liwat ang ginhiwat nga Pantawid Liwanag Program (PLP) cash assistance sa idalum sang programa nga Assistance for Indigents in Crisis Situation ukon (AICS) sang Department of Social Welfare and Development. Ang funding sa sini nga programa natigayon sa pagpanikasog man sang aton APEC Partylist. Ang mga benepisyaryo sang… Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more