• UNSCHEDULED POWER INTERRUPTION (SEPTEMBER 6, 2022)

    Date: September 6, 2022 Time of interruption: 5:45 PM Time of Restoration: 6:00 PM Affected Area: Sitio Carrida, San Lucas, Barotac Viejo Activity: Repair secondary load due to loose connection of side DX Transformer Supply 37.5 kVa and private transformer load side connection. We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (SEPTEMBER 6, 2022)

    Date: September 6, 2022 Time of interruption: 5:25 PM Time of Restoration: 5:53 PM Affected Area: Cabalic and Batuan, Balasan Activity: Inspection of lines and replaced busted fuselink. We apologize for the inconvenience. For your information. Read more

  • INSERTION OF ADDITIONAL POLE IN SITIO PUNTA, PEDADA, AJUY

    ILECO III Technical personnel conducted inserting additional pole due to the sagging of the conductor at Sitio Punta, Pedada, Ajuy today, September 6, 2022 (Tuesday). This activity is in line with the scheduled power interruption. Keep safe Warriors of Light For your information. Read more

  • PROMPT PAYING MCOs

    Thank you to our beloved Member-Consumer-Owners (MCOs) for paying your bills promptly. Keep safe always. *Masks were removed for documentation purposes only. #1ECMCOMovement#ParaSaOneECMCOMovement#ILECO3ServiceBeyondElectricity Read more

  • ILECO III Payment Centers

    Para sa mga individual Member – Consumer – Owners, puwede kamo makabayad sang ILECO III bills sa mga masunod nga accredited payment centers antes ukon sa natalana nga due date: – Palawan Pawnshop– M Lhuillier Pawnshop– RD Pawnshop– GCash– PayMaya– Union Bank– First Consolidated Bank (Estancia Branch Only)– BDO Network Branch (Sara and Estancia Branch… Read more

  • HAPPY FATHER’S DAY

    ILOILO III ELECTRIC COOPERATIVE, INC. celebrates Father’s Day, June 19, 2022 Happy Father’s Day to all (Tatay, Papa, Dad, Erpat) Read more

  • Happy Father’s Day sa tanan nga mga Tatay, Papa kag Daddy!

    Kamo ang matuod nga kusog kag haligi sang aton mga puluy-an. #1ECMCOMovement#ParaSaOneECMCOMovement#ILECO3CorporateSocialResponsibility#ILECO3ServiceBeyondElectricity ILECO III distributed tokens to honor the contribution of all Fathers in the society. *Masks were removed for documentation purposes only. Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more