• UPDATE ON UNSCHEDULED POWER INTERRUPTION As of April 27, 2023, 9:55 PM

    ILECO III Technical Team is still coordinating with National Grid Corporation of the Philippines (NGCP) and power suppliers for total power restoration of franchise coverage. We apologize for the inconvenience. For your information. Read more

  • NGCP MANUAL LOAD DROPPING

    Ginapahibalo ang tanan nga mga katapo-konsumidores sang ILECO III nga naga-implementar sang ROTATING POWER INTERRUPTION ang aton Kooperatiba bangud sang MANUAL LOAD DROPPING (MLD) sang National Grid Corporation of the Philippines (NGCP). Ang apektado sang rotational power interruption amo ang mga masunod nga lugar:ANILAO, BANATE, BAROTAC VIEJO, SAN RAFAEL, AJUY, SARA, LEMERY, CONCEPCION, SAN DIONISIO,… Read more

  • UPDATE ON UNSCHEDULED POWER INTERRUPTION As of April 27, 2023, 9:30 PM

    ILECO III Technical Team is still coordinating with National Grid Corporation of the Philippines (NGCP) and power suppliers for total power restoration of franchise coverage. We apologize for the inconvenience. For your information. Read more

  • ILECO III CONDUCTED ON-SITE PRE-MEMBERSHIP SEMINAR IN NHA VILLAGE, BACJAWAN SUR, CONCEPCION

    Instead of going to the Main Office at Preciosa, Sara, Iloilo, ILECO III conducted an on-site Pre-Membership Seminar to 116 applicants at NHA Village, Bacjawan Sur, Concepcion, Iloilo. This is the first step in applying an electric service connection. The regular pre-membership seminar is held at the Main Office every Tuesday & Thursday. Registration starts… Read more

  • IEC AND BAPA ASSEMBLY IN SITIO NABALAS, CULASI, AJUY

    ILECO III personnel conducted Information Education Campaign (IEC) and BAPA Assembly in Sitio Nabalas, Culasi, Ajuy, Iloilo with 100 attendees on July 27, 2022 (Wednesday). This meeting was conducted to inform the members of the status of BAPA operation as well as the important matters concerning our Cooperative. This information education campaign (IEC) is part… Read more

  • IEC AND BAPA ASSEMBLY IN NHA VILLAGE, BACJAWAN NORTE, CONCEPCION

    ILECO III personnel conducted Information Education Campaign (IEC) and BAPA Assembly in NHA Village, Bacjawan Norte, Concepcion, Iloilo with 104 attendees on July 26, 2022 (Tuesday). This meeting was conducted to inform the members of the status of BAPA operation as well as the important matters concerning our Cooperative. This information education campaign (IEC) is… Read more

  • ILECO III SAFETY TIPS SA PANAHON SANG TAG-ULAN

    1. Patyon ang Main Switch kung nagabaha na sa inyo lugar. 2. Indi pagtandugon ang mga basa nga wirings sang kuryente. 3. Indi magsaka sa mga kahoy bangud possible nga maglatay ang boltahe sang kuryente sa mga basa nga sanga. 4. Pagkatapos mabahaan ang inyo lugar, indi anay pagbuksan ang main switch. Magtawag sang accredited… Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more