• UNSCHEDULED POWER INTERRUPTION (SEPTEMBER 6, 2022)

    Date: September 6, 2022 Time of interruption: 5:25 PM Time of Restoration: 5:53 PM Affected Area: Cabalic and Batuan, Balasan Activity: Inspection of lines and replaced busted fuselink. We apologize for the inconvenience. For your information. Read more

  • INSERTION OF ADDITIONAL POLE IN SITIO PUNTA, PEDADA, AJUY

    ILECO III Technical personnel conducted inserting additional pole due to the sagging of the conductor at Sitio Punta, Pedada, Ajuy today, September 6, 2022 (Tuesday). This activity is in line with the scheduled power interruption. Keep safe Warriors of Light For your information. Read more

  • ENERGIZATION OF ALT GLOBAL IN POBLACION, ANILAO

    ILECO III Technical personnel conducted energization of Alt Global at Poblacion, Anilao today, September 6, 2022 (Tuesday). No Power Interruption Keep safe Warriors of Light For your information. Read more

  • HAPPY BIRTHDAY ADMIN JUANEZA!

    Happy birthday Admin. Emmanuel P. Juaneza, Administrator of National Electrification Administration (NEA). From ILECO III Family! National Electrification Administration (NEA) National Electrification Administration Read more

  • LIVE! CEREMONIAL SWITCH-ON OF THE 15TH MILLION CONSUMER ENERGIZED BY AN EC

    Witness the ceremonial switch-on of the 15th million consumer energized by an electric cooperative. https://www.facebook.com/aselco/videos/801883787836401/ Read more

  • Rural electrification at its best!

    Please tune in later to the live streaming of the ceremonial switch-on of the 15th million consumer energized by an electric cooperative. We, in ILECO III, together with the other 120 electric cooperatives (ECs) in the country, will continue to pursue our mandate of countryside development through rural electrification. https://www.facebook.com/OfficialNEA/posts/pfbid02CygcMsZpNk72gLMqpHBr5vZ8Do5oUor9cGJeCkdKuzHpXUCcc19dcKJMfqX16vyql Read more

  • PAANO MAG-GAMIT SANG PAYMAYA APP PARA SA PAGBAYAD SANG ILECO III BILLS

    Magabayad bala ikaw sang imo na bulanan nga bill sa PayMaya? Magsunod lang sa aton nga step by step nga proseso para mangin matawhay ang pagbayad sa aton nga Third Party Payment Center. Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more