• UNSCHEDULED POWER INTERRUPTION(NOVEMBER 3, 2022)

    Date: November 3, 2022 Time of interruption: 5:48 PM Time of Restoration: 6:56 PM Affected Area: Proper, San Lucas, Barotac Viejo Reason/Activity: Line fault due to vegetation/ Clearing of lines and repaired secondary bushing of 15kVa transformer supply. We apologize for the inconvenience. For your information. Read more

  • ENERGIZATION OF TRANSFORMER AND INSULATION OF THREE PHASE PRIVE TRANSFORMER IN BRGY. CANO-AN, ESTANCIA

    ILECO III Technical personnel conducted energization of Stephen T. Lao 3-25kVA Transformer and insulation of Three (3) Phase Private Transformer resulted to 4 to 5 hrs. of power interruption (under built) at Brgy. Cano-an, Estancia, today November 3, 2022 (Thursday). Keep safe Warriors of Light For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (NOVEMBER 3, 2022)

    Date: November 3, 2022 Time of interruption: 10:00 AM Time of Restoration: 11:30 AM Affected Area: Sitio Baldusano, Omio, Lemery Reason/Activity: Line fault due to vegetation/ Clearing of lines and repaired neutral cut-off We apologize for the inconvenience. For your information. Read more

  • HAPPY BIRTHDAY ADMIN JUANEZA!

    Happy birthday Admin. Emmanuel P. Juaneza, Administrator of National Electrification Administration (NEA). From ILECO III Family! National Electrification Administration (NEA) National Electrification Administration Read more

  • LIVE! CEREMONIAL SWITCH-ON OF THE 15TH MILLION CONSUMER ENERGIZED BY AN EC

    Witness the ceremonial switch-on of the 15th million consumer energized by an electric cooperative. https://www.facebook.com/aselco/videos/801883787836401/ Read more

  • Rural electrification at its best!

    Please tune in later to the live streaming of the ceremonial switch-on of the 15th million consumer energized by an electric cooperative. We, in ILECO III, together with the other 120 electric cooperatives (ECs) in the country, will continue to pursue our mandate of countryside development through rural electrification. https://www.facebook.com/OfficialNEA/posts/pfbid02CygcMsZpNk72gLMqpHBr5vZ8Do5oUor9cGJeCkdKuzHpXUCcc19dcKJMfqX16vyql Read more

  • PAANO MAG-GAMIT SANG PAYMAYA APP PARA SA PAGBAYAD SANG ILECO III BILLS

    Magabayad bala ikaw sang imo na bulanan nga bill sa PayMaya? Magsunod lang sa aton nga step by step nga proseso para mangin matawhay ang pagbayad sa aton nga Third Party Payment Center. Read more

  • ITB 2204, S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB, 2203 S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB 2202, S. 2022

    Procurement of Poles Read more