• EMERGENCY POWER INTERRUPTION (AUGUST 15, 2022)

    Date: August 15, 2022 Time of interruption: 9:42 AM Time of Restoration: 3:00 PM Affected Area: Sitio Ga-on, Brgy. Bato Biasong, Ajuy Activity: Pole hauling and erection of pole replacement of damage/rotten pole We apologize for the inconvenience. For your information. P.S We are grateful to Brgy. Captain Asturias and officials of the said barangay… Read more

  • UNSCHEDULED POWER INTERRUPTION (AUGUST 18, 2022)

    Date: August 18, 2022 Time of interruption: 9:04 AM Time of Restoration: 10:10 AM Affected Area: Tabugon Island, Carles Cause of Interruption: Transient line fault Activity: Inspection of lines and replaced busted fuselink We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (AUGUST 18, 2022)

    Date: August 18, 2022 Time of interruption: 8:15 AM Time of Restoration: 9:05 AM Affected Area: Sitio Lampuyang, Sitio Danmar and Sitio Bacolod, Libertad, Banate Cause of Interruption: Line fault due to animal contact (bat) Activity: Inspection/clearing of lines and replaced busted fuselink We apologize for the inconvenience. For your information. Read more

  • ILECO III TRIVIA Question #5

    Maghatag sang tatlo (3) ka rason sang NATALANA NGA POWER INTERRUPTION: (In any order) Read more

  • SCHEDULE OF DUE DATES AND DISCONNECTION FOR THE MONTH OF SEPTEMBER 2022

    For your information. Read more

  • ILECO III TRIVIA FACT #11

    Transmission – ini ang ginadumala ukon ginamintenar sang National Grid Corporation of the Philippines o (NGCP) nga gina-agyan sang kuryente halin sa Generation Plants pakadto sa mga Distribution Utilities kaangay sang ILECO III. Ini ang nagaserbi bilang “highway” pakadto sa mga substations sang ILECO III. #ILECO3@36#IbaAngMayAlam Read more

  • ILECO III TRIVIA QUESTION #4

    Ano ang portion sang bill nga nagakadto gid lamang sa Distribution Utility kaangay sang ILECO III para magamit sa operasyon kag maintenance expenses. Ini nagabalor PhP 1.4640 halin pag-implementar sang tuig 2009? #ILECOIII@36#IbaAngMayAlam Read more

  • ITB 2204, S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB, 2203 S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB 2202, S. 2022

    Procurement of Poles Read more