• EMERGENCY POWER INTERRUPTION (AUGUST 15, 2022)

    Date: August 15, 2022 Time of interruption: 9:42 AM Time of Restoration: 3:00 PM Affected Area: Sitio Ga-on, Brgy. Bato Biasong, Ajuy Activity: Pole hauling and erection of pole replacement of damage/rotten pole We apologize for the inconvenience. For your information. P.S We are grateful to Brgy. Captain Asturias and officials of the said barangay… Read more

  • UNSCHEDULED POWER INTERRUPTION (AUGUST 18, 2022)

    Date: August 18, 2022 Time of interruption: 9:04 AM Time of Restoration: 10:10 AM Affected Area: Tabugon Island, Carles Cause of Interruption: Transient line fault Activity: Inspection of lines and replaced busted fuselink We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (AUGUST 18, 2022)

    Date: August 18, 2022 Time of interruption: 8:15 AM Time of Restoration: 9:05 AM Affected Area: Sitio Lampuyang, Sitio Danmar and Sitio Bacolod, Libertad, Banate Cause of Interruption: Line fault due to animal contact (bat) Activity: Inspection/clearing of lines and replaced busted fuselink We apologize for the inconvenience. For your information. Read more

  • Trivia Question #8

    Maghatag sang lima (5) ka banwa nga nasakupan sang Sara Area Office (SAO). Read more

  • ILECO III Trivia Fact#16

    Ang apat (4) ka banwa nga yara sa area coverage sang Natividad Area Office ukon (NAO) amo ang mga masunod: AnilaoBanateBarotac ViejoSan Rafael Read more

  • SARADO ANG OPISINA SANG ILECO MAIN OFFICE KAG AREA OFFICES SA SETYEMBRE 26, 2022

    Pahibalo sa mga katapo-konsumidores nga ang ILECO III ang naga-selebrar sang 36th Founding Anniversary sa SETYEMBRE 26, 2022 (LUNES). Bangud sini, SARADO ANG ILECO III MAIN OFFICE kag AREA OFFICES (Sara, Natividad kag Pani-an) sa nasambit nga adlaw.May ara sang assigned on duty maintenance crew sa kada Area Offices para sa pag-responde sa inyo nga… Read more

  • ILECO III Trivia Question #7

    Ano ang tawag sa ginadumala ukon ginamintenar sang National Grid Corporation of the Philippines o (NGCP) nga gina-agyan sang kuryente halin sa Generation Plants pakadto sa mga Distribution Utilities kaangay sang ILECO III. Ini ang nagaserbi bilang “highway” pakadto sa mga substations sang ILECO III? Read more

  • ITB 2204, S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB, 2203 S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB 2202, S. 2022

    Procurement of Poles Read more