• UNSCHEDULED POWER INTERRUPTION (FEBRUARY 26, 2023)

    Date: February 26, 2023 Time of interruption: 5:00 AM Time of restoration (Libertad): 5:30 AM Time of restoration (Magdalo): 6:15 AM Affected areas: Libertad and Magdalo, Banate, Iloilo Activities: Inspection of line and and refusing We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (FEBRUARY 25, 2023 – UPDATE)

    Date: February 25, 2023 Substation: Banate Substation Time of interruption: 8:18 PM Time of Restoration: 9:45 PM for Feeder 3 of Banate Substation Affected area: Portion of Municipality of Banate Reason: Damage Insulator at Sitio Gawahon Libertad, Banate We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (FEBRUARY 25, 2023)

    Date: February 25, 2023 Substation: Banate Substation Time of interruption: 8:18 PM Time of restoration: 8:21 PM for Feeder 1 and Feeder 2 of Banate Substation Feeder 3 (not yet energized). Ileco 3 Technical team traces up and determines the reason for the fault. Affected area: Municipality of Banate and Anilao Reason: Lock out ground… Read more

  • ENERGY CONSERVATION TIPS!

    AIR CONDITIONING UNIT Buy an aircon with high Energy Efficiency. Ratio indicated in the yellow label.Change or clean your AC’s air filters regularly.Block the sun from overheating your home. Inside, use shades, blinds and drapes.Outside, use awnings, trees and shrubs.Repair leaky ducts to reduce heating and cooling costs.Decorate for a cooler home by hanging light-colored… Read more

  • SCHEDULE OF DUE DATES AND DISCONNECTION FOR THE MONTH OF JANUARY 2023

    For your information. Thank you! Read more

  • NOTICE TO THE PUBLIC

    Pahibalo sa mga katapo-konsumidores nga pagakwa-on ang tanan nga mga unauthorized cables/wires sang mga unregistered Telco/Internet Providers nga naga-attach sa ILECO III distribution lines kag poles nga wala sang pahanugot halin sa aton kooperatiba. Ang opisina ang magahatag lamang sang plaso asta sa Enero 31, 2023 (Martes) para makuha ang mga cables/wires. Dugang diri, kung… Read more

  • ILECO III WEATHER ADVISORY

    Ginapahibalo ang tanan nga mga miyembro-konsumidores sang ILECO III nga kita ang gaka-ekperiensya sang madamol nga pag-ulan sa iban nga bahin sang aton franchise coverage. Kita tanan ang mag-halong para sa aton seguridad kag pamilya. May ara kita Maintenance Team nga naka-assign sa tanan nga Area Offices para sa pag-restore sang power sa mga apektado… Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more