• UNSCHEDULED POWER INTERRUPTION (SEPTEMBER 8, 2022)

    Date: September 8, 2022 Time of interruption: 7:21 PM Time of Restoration: 7:44 PM Affected Area: Binon-an, Alinsolong and Ban-Ban, Batad Activity: Inspection of line and replaced busted fuselink We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (SEPTEMBER 8, 2022)

    Date: September 8, 2022 Time of interruption: 6:56 AM Time of Restoration: 9:15 AM Affected Area: Tabugon Proper and Tabugon Minor, Carles (Island) Activity: Inspection of line and replaced busted fuselink and change defective kWhr Meter We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (SEPTEMBER 7, 2022)

    Date: September 7, 2022 Time of interruption: 7:05 PM Time of Restoration: 7:35 PM Affected Area: Sitio Cawayan Sulod, Cawayan, Carles Activity: Inspection of line and replaced busted fuselink We apologize for the inconvenience. For your information. Read more

  • ANO ANG MANUAL LOAD DROPPING?

    Read more

  • SENIOR CITIZEN DISCOUNT

    Pahibalo sa mga katapo konsumidores sang ILECO III nga may ara sang 5% nga diskwento para sa aton mga Senior Citizens nga naga-konsumo sang indi maglapaw sa 100 kwhr kag nakapa-miyembro na sa kooperatiba indi magnubo sa isa ka tuig.Ipasa ang mga masunod nga requirements sa pinakamalapit nga Area Office sang ILECO III:• Valid Senior… Read more

  • Paano ang pag-report sang complaints sa ILECO III?

    1. Magtawag ukon mag-text.ILECO III Contact Numbers:SARA AREA OFFICE – 0919-069-7391NATIVIDAD AREA OFFICE – 0919-069-7403PANI-AN AREA OFFICE – 0919-069-7396Kalakip ang mga masunod nga impormasyon:PANGALAN kag ADDRESS 2. Magpadala sang mensahe sa ILECO III Facebook Page.Kalakip ang mga masunod nga impormasyon:PANGALANADDRESSCONTACT NUMBER 3. Magbisita sa Area Office.ILECO III OFFICE HOURS:LUNES- BIYERNES8:00 AM- 5:00 PM12:00 NN- LUNCHBREAK… Read more

  • NGAA MAY POWER INTERRUPTION?

    Ang power interruption amo ang temporaryo nga pag-untat sang supply sang kuryente sa isa ka lugar ukon balay. May duha ka sahi sang power interruption: 1. NATALANA (SCHEDULED)2. WALA NATALANA (UNSCHEDULED) Mga rason nga-a may ara sang scheduled power interruption: • Pagkay-o sang makinaryas• Pagkay-o kag pagmentinar sang linya sang kuryente• Line Clearing Activities• Pag-relocate… Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more