• UPDATE ON UNSCHEDULED POWER INTERRUPTIONAs of April 27, 2023, 3:45 PM

    ILECO III Technical Team is still coordinating with National Grid Corporation of the Philippines (NGCP) and power suppliers for total power restoration of franchise coverage. We apologize for the inconvenience. For your information. Read more

  • NGCP’s UNSCHEDULED POWER INTERRUPTION AFFECTING WHOLE PANAY ISLAND (APRIL 27, 2023)

    DATE: April 27, 2022 (Thursday)Time of interruption: 1:53 PMEstimated Time of power restoration: NOT YET DETERMINED Affected areas: ILECO III Coverage Area (Sara, Lemery, Ajuy, San Dionisio, Concepcion, Batad, Estancia, Balasan, Carles, Anilao, Banate, Barotac Viejo and San Rafael) Cause of interruption: Over voltage of transmission line of NGCP caused by tripping of power generation… Read more

  • SCHEDULED POWER INTERRUPTION SA ABRIL 29, 2023

    Pahibalo sa mga katapo-konsumidores nga may SCHEDULED POWER INTERRUPTION ang ILECO III para sa patigayunon nga clearing sang linya (backbone kag lateral lines), Pag-relocate sang Single Phase Line kag Replacement sang gabok nga mga poste. Ang oras, petsa kag apektado nga mga lugar sang sini nga power interruption amo ang masunod: ABRIL 29, 2023 (SABADO)8:00… Read more

  • ENERGY SAVING TIP

    Unplug devices when not in use. Read more

  • REQUIREMENTS FOR CHANGE OF NAME (DECEASED MEMBER CONSUMER)

    1. For Spouse Applicants• Death Certificate of Member-Consumer/ BarangayCertification provided by ILECO III signedby Punong Barangay• Marriage Contract• Proof of Ownership – (e.g. deed of sale, affidavit ofheirship) (if available)2. For Legal Heirs• Death Certificate of Member-Consumer/ BarangayCertification provided by ILECO III• Notarized Waiver of Rights stating that the othersuccessors are not after on the… Read more

  • ANTI-OBSTRUCTION OF POWER LINES ACT(REPUBLIC ACT 11361)

    ‘An Act Ensuring the Continuous and Uninterrupted Transmission and Distribution of Electricity and Protection of the Integrity and Reliability of Power Lines, and Providing Penalties for Violations Thereof.’ Ginadumili-an ang mga masunod: 1. Pagtanom sang maskin ano nga sahi sang matag-as ukon naga-taas nga mga tanom ukon kahoy sa idalom sang distribution lines. 2. Pagpatindog… Read more

  • ANO ANG MANUAL LOAD DROPPING?

    Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more