• NGCP’s UNSCHEDULED POWER INTERRUPTION (OCTOBER 10, 2022)

    DATE: October 10, 2022 (Monday)Time of interruption: 7:43 AMEstimated Time of power restoration: 7:50 AMAffected areas: Whole Coverage of Natividad Area (Anilao, Banate, Barotac Viejo and San Rafael)Cause of interruption: 69kV transmission line of NGCP. Not yet determined We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (OCTOBER 6, 2022)

    Date: October 6, 2022Time of interruption: 8:15 PMTime of Restoration: 9:03 PMAffected Area: Punta, CarlesActivity: Inspection/clearing on the primary lines due to vegetation and replace fuselinkWe apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (OCTOBER 6, 2022)

    Date: October 6, 2022 Time of interruption: 10:00 AM Time of Restoration: 12:15 PM Affected Area: Portion of Merced, Banate Activity: Fixing the sagging of the secondary line and clearing of lines affecting the two (2) span distribution pole due to vegetation We apologize for the inconvenience. For your information. Read more

  • ENERGY SAVING TIP

    Dry your clothes and dishes naturally. Read more

  • FREQUENTLY ASKED QUESTIONS

    ANO ANG REQUIREMENTS KUNG MAG-APPLY SANG CHANGE OF NAME? Read more

  • ACCREDITED THIRD PARTY COLLECTION CENTERS

    PAHIBALO SA MGA KATAPO-KONSUMIDORES Ang tanan nga individual consumers ang pwede makabayad sa mga masunod nga accredited payment centers:PAYMAYAECPAYLINK.BIZPORTALUNION BANKSEVEN ELEVENFIRST CONSOLIDATED BANK- ESTANCIA BRANCHGCASHBDO NETWORK BANK- ESTANCIA AND SARA BRANCHRD PAWNSHOPM LHUILLIERUNIFIED GPRSPALAWAN PAWNSHOPRURAL BANK OF ANILAO, INC.BDO UNIBANKRCBCSamtang ang tanan nga BAPA Members ang kinahanglan nga magbayad sa inyo natungdan nga BAPA.Madamo gid… Read more

  • ENERGY SAVING TIP

    Clean your fridge and avoid opening it longer than necessary. Read more

  • ITB 2209, S. 2022

    Procurement of Materials for Construction of Distribution Lines and Supply, Delivery and Installation of Kwhr Meter for Sitio Electrification Program (SEP) – Forty Four (44) Sitios Read more

  • ITB 2208, S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB 2207, S. 2022

    Re-Bidding of the Procurement of Materials and Equipment for Change Meter/Rehabilitation, Service Drop Installation, Housewiring Land and Maintenance Use Read more