• EMERGENCY POWER INTERRUPTION (AUGUST 15, 2022)

    Date: August 15, 2022 Time of interruption: 9:42 AM Time of Restoration: 3:00 PM Affected Area: Sitio Ga-on, Brgy. Bato Biasong, Ajuy Activity: Pole hauling and erection of pole replacement of damage/rotten pole We apologize for the inconvenience. For your information. P.S We are grateful to Brgy. Captain Asturias and officials of the said barangay… Read more

  • UNSCHEDULED POWER INTERRUPTION (AUGUST 18, 2022)

    Date: August 18, 2022 Time of interruption: 9:04 AM Time of Restoration: 10:10 AM Affected Area: Tabugon Island, Carles Cause of Interruption: Transient line fault Activity: Inspection of lines and replaced busted fuselink We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (AUGUST 18, 2022)

    Date: August 18, 2022 Time of interruption: 8:15 AM Time of Restoration: 9:05 AM Affected Area: Sitio Lampuyang, Sitio Danmar and Sitio Bacolod, Libertad, Banate Cause of Interruption: Line fault due to animal contact (bat) Activity: Inspection/clearing of lines and replaced busted fuselink We apologize for the inconvenience. For your information. Read more

  • GOOD FRIDAY

    ILOILO III ELECTRIC COOPERATIVE, INC. observes Good Friday, April 07, 2023 Read more

  • MAUNDY THURSDAY

    ILOILO III ELECTRIC COOPERATIVE, INC. observes Maundy Thursday, April 06, 2023 Read more

  • MAGPAREHISTRO NA SA ATON 31ST AGMA

    ILOILO III ELECTRIC COOPERATIVE, INC. 31st VIRTUAL ANNUAL GENERAL MEMBERSHIP ASSEMBLY Link for Registration: https://forms.gle/1xEEg6uTxFaCxmhk9 https://forms.gle/aexZrv4zhbcBSn4X8 https://forms.gle/Wa8JXiYagacCoBcm6 Read more

  • ILECO 3 HOLY WEEK SCHEDULE

    PAHIBALO SA MGA KATAPU-KONSUMIDORES ILECO 3 Holy Week Schedule Read more

  • ITB 2209, S. 2022

    Procurement of Materials for Construction of Distribution Lines and Supply, Delivery and Installation of Kwhr Meter for Sitio Electrification Program (SEP) – Forty Four (44) Sitios Read more

  • ITB 2208, S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB 2207, S. 2022

    Re-Bidding of the Procurement of Materials and Equipment for Change Meter/Rehabilitation, Service Drop Installation, Housewiring Land and Maintenance Use Read more