• UNSCHEDULED POWER INTERRUPTION (FEBRUARY 26, 2023)

    Date: February 26, 2023 Time of interruption: 5:00 AM Time of restoration (Libertad): 5:30 AM Time of restoration (Magdalo): 6:15 AM Affected areas: Libertad and Magdalo, Banate, Iloilo Activities: Inspection of line and and refusing We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (FEBRUARY 25, 2023 – UPDATE)

    Date: February 25, 2023 Substation: Banate Substation Time of interruption: 8:18 PM Time of Restoration: 9:45 PM for Feeder 3 of Banate Substation Affected area: Portion of Municipality of Banate Reason: Damage Insulator at Sitio Gawahon Libertad, Banate We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (FEBRUARY 25, 2023)

    Date: February 25, 2023 Substation: Banate Substation Time of interruption: 8:18 PM Time of restoration: 8:21 PM for Feeder 1 and Feeder 2 of Banate Substation Feeder 3 (not yet energized). Ileco 3 Technical team traces up and determines the reason for the fault. Affected area: Municipality of Banate and Anilao Reason: Lock out ground… Read more

  • MAUNDY THURSDAY

    ILOILO III ELECTRIC COOPERATIVE, INC. observes Maundy Thursday, April 06, 2023 Read more

  • MAGPAREHISTRO NA SA ATON 31ST AGMA

    ILOILO III ELECTRIC COOPERATIVE, INC. 31st VIRTUAL ANNUAL GENERAL MEMBERSHIP ASSEMBLY Link for Registration: https://forms.gle/1xEEg6uTxFaCxmhk9 https://forms.gle/aexZrv4zhbcBSn4X8 https://forms.gle/Wa8JXiYagacCoBcm6 Read more

  • ILECO 3 HOLY WEEK SCHEDULE

    PAHIBALO SA MGA KATAPU-KONSUMIDORES ILECO 3 Holy Week Schedule Read more

  • HAPPY BIRTHDAY DIRECTOR BELITA!

    Happy happy birthday to our dear Board of Director, Engr. Vincent H. Belita. Wishing you all the best in life and may God bless you always. From your ILECO III Family! Read more

  • ITB 2209, S. 2022

    Procurement of Materials for Construction of Distribution Lines and Supply, Delivery and Installation of Kwhr Meter for Sitio Electrification Program (SEP) – Forty Four (44) Sitios Read more

  • ITB 2208, S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB 2207, S. 2022

    Re-Bidding of the Procurement of Materials and Equipment for Change Meter/Rehabilitation, Service Drop Installation, Housewiring Land and Maintenance Use Read more