• NGCP’s UNSCHEDULED POWER INTERRUPTION

    DATE: July 06, 2023 (Thursday) Time of interruption:Ajuy S/s: 9:00PMSara S/s: 9:00 PMPani-an S/s: 9:01 PMDaan Banwa S/s: 9:00 PM Estimated Time of power restoration: Sara S/s: 9:10 PMAjuy S/s: 9:08 PMPani-an S/s: 9:13 PMDaan Banwa S/s: 9:15 PM Affected areas: Whole coverage of ILECO III Cause of interruption: UNDER INVESTIGATION Our technical team is… Read more

  • NGCP’s UNSCHEDULED POWER INTERRUPTION (UPDATE)

    DATE: July 05, 2023 (Wednesday) Time of interruption:Barotac Viejo S/s: 8:50 PMBanate S/s: 8:50 PM Estimated Time of power restoration: Barotac Viejo S/s : 9:05 PMBanate S/s: 9:06 PM Affected areas: Anilao, Banate, Barotac Viejo and San Rafael Cause of interruption: UNDER INVESTIGATION Our technical team is closely coordinating with NGCP regarding the cause of… Read more

  • NGCP’s UNSCHEDULED POWER INTERRUPTION

    DATE: July 05, 2023 (Wednesday) Time of interruption:Barotac Viejo S/s: 8:50 PMBanate S/s: 8:50 PM Estimated Time of power restoration: NOT YET DETERMINED Affected areas: Anilao, Banate, Barotac Viejo and San Rafael Cause of interruption: UNDER INVESTIGATION Our technical team is closely coordinating with NGCP for the power restoration. We apologize for the inconvenience. For… Read more

  • FIRE SAFETY TIP

    Know how to use a fire extinguisher. Read more

  • FREQUENTLY ASKED QUESTION

    ANO ANG MGA ACCREDITED PAYMENT CENTERS SANG ILECO III? *Para lamang ini sa mga individual Member-Consumer-Owners. Ang BAPA Members ang kinahanglan magbayad sa ila natungdan nga BAPA. Read more

  • FIRE SAFETY TIP

    Avoid overnight charging. Read more

  • SENIOR CITIZEN DISCOUNT

    Pahibalo sa mga katapo konsumidores sang ILECO III nga may ara sang 5% nga diskwento para sa aton mga Senior Citizens nga naga-konsumo sang indi maglapaw sa 100 kwhr kag nakapa-miyembro na sa kooperatiba indi magnubo sa isa ka tuig.Ipasa ang mga masunod nga requirements sa pinakamalapit nga Area Office sang ILECO III: • Valid… Read more

  • ITB 2209, S. 2022

    Procurement of Materials for Construction of Distribution Lines and Supply, Delivery and Installation of Kwhr Meter for Sitio Electrification Program (SEP) – Forty Four (44) Sitios Read more

  • ITB 2208, S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB 2207, S. 2022

    Re-Bidding of the Procurement of Materials and Equipment for Change Meter/Rehabilitation, Service Drop Installation, Housewiring Land and Maintenance Use Read more