• CLEARING OPERATION DUE TO VEGETATION ON THE SECONDARY LINE IN AGPIPILI, LEMERY

    ILECO III Technical personnel conducted clearing operation due to vegetation on the secondary line at Agpipili, Lemery, today November 1, 2022 (Tuesday). No Power InterruptionKeep safe Warriors of Light For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION DUE TO CONTACT OF INSERTED TELCO POLES IN OUR DISTRIBUTION LINES

    We would like to inform our beloved member consumers that Sara Substation Feeder 1 is currently experiencing unscheduled trip-off due to contact of inserted TELCO poles in our distribution lines. ILECO III is now coordinating with TELCOs for a meeting to discuss solutions to the said problem. Afftected Areas: Sara Substation (Feeder 1)Sara: Aldeguer and… Read more

  • EMERGENCY POWER INTERRUPTION (NOVEMBER 1, 2022)

    Date: November 1, 2022 Time of interruption: 8:12 AM Time of Restoration: 8:42 AM Affected Area: Whole Feeder 1 of Sara Substation (Brgys of Sara and San Dionisio) Afftected Areas: Sara Substation (Feeder 1)Sara: Aldeguer and Castor (Portion)San Dionisio: Dugman, Tuble, San Nicolas, Cudionan, Had. Conchita, Sua, Tiabas, Cubay, Bagacay, Agdaliran, Borongon, Manduawak, Talo-ato, Batuan,… Read more

  • LOOK: ILECO III-THE FIRST EC WITH THE MOST NUMBER OF LINEMEN CERTIFIED AS COMPETENT BY TESDA FOR EPDLC-NCII IN VISAYAS

    Forty (40) out of 43 linemen of ILECO III had passed the TESDA competency assessment for Electric Power Distribution Line Construction NC II last June 6-9, 2023 at TESDA Accredited Assessment Center, Iloilo III Electric Cooperative, Inc., Brgy. Preciosa, Sara, Iloilo. The Assessment was conducted by TESDA Accredited Assessor, Engr. Rodel F. Anado of GUIMELCO… Read more

  • ENERGY SAVING TIP

    Clean your fridge and avoid opening it longer necessary. Read more

  • NOTICE TO THE PUBLIC

    Pahibalo sa mga katapo-konsumidores nga ang HUNYO 12, 2023 (LUNES) ang gin-deklara nga REGULAR HOLIDAY sa bug-os nga pungsod para sa pag-obserba sang INDEPENDENCE DAY. Bangud sini, SARADO ang ILECO III Main Office SARA AREA OFFICE kag NATIVIDAD AREA OFFICE sa nasambit nga adlaw. Apang BUKAS ang PANI-AN AREA OFFICE para sa pagbaton sang bayad… Read more

  • ENERGY SAVING TIP

    Use natural light when possible. Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more