• UNSCHEDULED POWER INTERRUPTION (FEBRUARY 26, 2023)

    Date: February 26, 2023 Time of interruption: 5:00 AM Time of restoration (Libertad): 5:30 AM Time of restoration (Magdalo): 6:15 AM Affected areas: Libertad and Magdalo, Banate, Iloilo Activities: Inspection of line and and refusing We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (FEBRUARY 25, 2023 – UPDATE)

    Date: February 25, 2023 Substation: Banate Substation Time of interruption: 8:18 PM Time of Restoration: 9:45 PM for Feeder 3 of Banate Substation Affected area: Portion of Municipality of Banate Reason: Damage Insulator at Sitio Gawahon Libertad, Banate We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (FEBRUARY 25, 2023)

    Date: February 25, 2023 Substation: Banate Substation Time of interruption: 8:18 PM Time of restoration: 8:21 PM for Feeder 1 and Feeder 2 of Banate Substation Feeder 3 (not yet energized). Ileco 3 Technical team traces up and determines the reason for the fault. Affected area: Municipality of Banate and Anilao Reason: Lock out ground… Read more

  • LOOK: ILECO III-THE FIRST EC WITH THE MOST NUMBER OF LINEMEN CERTIFIED AS COMPETENT BY TESDA FOR EPDLC-NCII IN VISAYAS

    Forty (40) out of 43 linemen of ILECO III had passed the TESDA competency assessment for Electric Power Distribution Line Construction NC II last June 6-9, 2023 at TESDA Accredited Assessment Center, Iloilo III Electric Cooperative, Inc., Brgy. Preciosa, Sara, Iloilo. The Assessment was conducted by TESDA Accredited Assessor, Engr. Rodel F. Anado of GUIMELCO… Read more

  • ENERGY SAVING TIP

    Clean your fridge and avoid opening it longer necessary. Read more

  • NOTICE TO THE PUBLIC

    Pahibalo sa mga katapo-konsumidores nga ang HUNYO 12, 2023 (LUNES) ang gin-deklara nga REGULAR HOLIDAY sa bug-os nga pungsod para sa pag-obserba sang INDEPENDENCE DAY. Bangud sini, SARADO ang ILECO III Main Office SARA AREA OFFICE kag NATIVIDAD AREA OFFICE sa nasambit nga adlaw. Apang BUKAS ang PANI-AN AREA OFFICE para sa pagbaton sang bayad… Read more

  • ENERGY SAVING TIP

    Use natural light when possible. Read more

  • ITB 2209, S. 2022

    Procurement of Materials for Construction of Distribution Lines and Supply, Delivery and Installation of Kwhr Meter for Sitio Electrification Program (SEP) – Forty Four (44) Sitios Read more

  • ITB 2208, S. 2022

    Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more

  • ITB 2207, S. 2022

    Re-Bidding of the Procurement of Materials and Equipment for Change Meter/Rehabilitation, Service Drop Installation, Housewiring Land and Maintenance Use Read more