• UNSCHEDULED POWER INTERRUPTION (MAY 16, 2023)

    Date: May 16, 2023 Time of interruption: 10:30 AM Time of restoration: 11:10 AM Affected area: Poblacion Market, Sara, Iloilo (portion) Activity: Installed 50 kVA distribution transformer We apologize for the inconvenience. For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION (MAY 11, 2023)

    Date: May 11, 2023 Time of interruption: 12:15 PM Time of restoration: 1:45 PM Affected area: Culasi, Ajuy, Iloilo (portion) Activity: Replacement of rotten pole We apologize for the inconvenience. For your information. Read more

  • SCHEDULED POWER INTERRUPTION SA MAYO 12 KAG 13, 2023 SA BANWA SANG CARLES

    Pahibalo sa mga katapo-konsumidores nga may SCHEDULED POWER INTERRUPTION ang ILECO III para sa pag-patigayon sang technical activities. Ang petsa, oras kag lugar nga apektado sang sini nga power interruptions sa banwa sang CARLES amo ang masunod: MAY 12, 2023 (BIYERNES)8:00 AM- 5:00 PM (9 ka oras ang kalawigon)• Brgy. Granada• Brgy. Asluman MAY 13,… Read more

  • Congratulations to all Warriors of Light!

    Power On! Read more

  • ANTI-OBSTRUCTION OF POWER LINES ACT

    (REPUBLIC ACT 11361) ‘An Act Ensuring the Continuous and Uninterrupted Transmission and Distribution of Electricity and Protection of the Integrity and Reliability of Power Lines, and Providing Penalties for Violations Thereof.’ Ginadumili-an ang mga masunod: 1. Pagtanom sang maskin ano nga sahi sang matag-as ukon naga-taas nga mga tanom ukon kahoy sa idalom sang distribution… Read more

  • SENIOR CITIZEN DISCOUNT

    Pahibalo sa mga katapo konsumidores sang ILECO III nga may ara sang 5% nga diskwento para sa aton mga Senior Citizens nga naga-konsumo sang indi maglapaw sa 100 kwhr kag nakapa-miyembro na sa kooperatiba indi magnubo sa isa ka tuig.Ipasa ang mga masunod nga requirements sa pinakamalapit nga Area Office sang ILECO III: • Valid… Read more

  • ILECO III ENERGY SAVING TIPS

    Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more