POWER RATES
POWER ADVISORIES
Ang aton mga substations nga na energize ang nag-off line sa liwat subong alas 9:08 a.m. bangud sang pag-tripping sang planta sang PEDC nga nagdulot sang unstable nga supply sang kuryente sa bug-os nga Panay power grid. Sara Substation- De-Energized Ajuy Substation – De-Energized Banate Substation -De-Energized Balasan Substation -De-Energized Daan Banwa Substation – Not… Read more
Nag abiso ang PEDC nga nagtripped and ila nga unit 1 & 3 kag yara na sa under investigation ang status sang ila nga mga planta alas 2:39 kagina sang kaagahon. Nag paguwa naman sa liwat ang PEDC sang update alas 6:00 kagina sang aga nga nasynchronize na nila liwat ang Unit 1 nila ng… Read more
SARA SUBSTATION BANATE SUBSTATION DAAN BANWA AJUY SUBSTATION NATIVIDAD SUBSTATION was de-energized due to NGCP shutdown. ILECO III Technical Team is still closely coordinating with National Grid Corporation of the Philippines (NGCP) and power suppliers for total power restoration of franchise coverage. Power restoration to affected areas is not yet determined. We apologized for the… Read more
NEWS AND UPDATES
PAHIBALO SA MGA KATAPO-KONSUMIDORES SANG ILECO III Para sa mga individual Member-Consumer-Owners, puwede na makabayad sang ILECO III bills sa UNIVERSAL STOREFRONT SERVICES CORPORATION (USSC) antes ukon sa natalana nga due date. Madamo gid nga salamat sa padayon nga suporta sa aton kooperatiba. Read more
For your information. Read more
This meeting was conducted to inform the members of the status of BAPA operation as well as the important matters concerning our Cooperative. This information education campaign (IEC) is part of ILECO III’s empowerment program of our member-consumer-owners (MCOs) and to be pro-active to all activities conducted by our cooperative. For your information. National Electrification… Read more
Some of the agenda presented to the above-mentioned attendees were the following:a. Status of Operationb. Damaged Solar PVMc. Coop Updatesd. Open ForumThe Information Education Campaign (IEC) is part of ILECO III’s empowerment program to our Member-Consumer-Owners. Series of meetings were conducted to inform the members of the status of operation and important matters concerning our… Read more
BIDS AND NOTICES
Procurement of Materials for Construction of Distribution Lines and Supply, Delivery and Installation of Kwhr Meter for Sitio Electrification Program (SEP) – Forty Four (44) Sitios Read more
Procurement of Materials and Labor for the Extension of Distribution Lines for Five (5) NHA Yolanda Permanent Resettlement Sites (A Turn-Key Project) Read more
Re-Bidding of the Procurement of Materials and Equipment for Change Meter/Rehabilitation, Service Drop Installation, Housewiring Land and Maintenance Use Read more