• UNSCHEDULED POWER INTERRUPTION

    Date: May 30, 2024 (Thursday) Time of interruption: 12:27 PM Time of restoration: 1:17 PM Affected areas: Sara S/S Feeder 1- Sara (portion) and San Dionisio, Iloilo Cause: Tree felled on the Primary Line due to cutting activities done by our MCO For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION

    Date: May 30, 2024 Time of interruption: 5:20 AM Time of restoration: 6:01 AM Affected area: Culasi, Ajuy, Iloilo Cause: Line fault due to animal contact For your information. Read more

  • UNSCHEDULED POWER INTERRUPTION

    Date: May 29, 2024 Time of interruption: 3:43 PM Time of restoration: 4:20 PM Affected area: Maya, Balasan, Iloilo (portion) Activity: Installed additional distribution transformer For your information Read more

  • HAPPY BIRTHDAY MAYOR VILLEGAS!

    Happy birthday HON. OSCAR C. VILLEGAS, JR., Municipal Mayor- Lemery, Iloilo. From ILECO III Family! Read more

  • LOOK: ILECO III CONDUCTED IEC AND GIFT GIVING ACTIVITY

    ILECO III successfully conducted Information Education Campaign (IEC) and Gift-giving Activity to 44 BAPA members in Sitio Hurog, Jamul-awon, Concepcion, Iloilo on August 25, 2023 (Friday). The said meeting was attended and headed by SAO-Branch Operation Service Chief Mr. Manuel S. Espinosa II, MCO-WD Chief Mr. Alex A. Demandante and assisted by other ILECO III Read more

  • SAFETY TIPS SA PANAHON SANG TAG-ULAN

    1. Patyon ang Main Switch kung nagabaha na sa inyo lugar.2. Indi pagtandugon ang mga basa nga wirings sang kuryente.3. Indi magsaka sa mga kahoy bangud possible nga maglatay ang boltahe sang kuryente sa mga basa nga sanga.4. Pagkatapos mabahaan ang inyo lugar, indi anay pagbuksan ang main switch. Magtawag sang accredited barangay electrician para Read more

  • LOOK: ILECO III CONDUCTED IEC AND GIFT GIVING ACTIVITY

    ILECO III successfully conducted Information Education Campaign (IEC) and Gift-giving Activity to 38 BAPA members in Sitio Linusot, Poblacion, San Rafael, Iloilo on August 23, 2023 (Wednesday). The said meeting was attended and headed by NAO-Branch Operation Service Chief Ms. Ma. Angela P. Resano and assisted by other ILECO III personnel. This is one of Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more