• POWER RESTORATION UPDATE

    As of 12:30 AM, March 2, 2024 Power was FULLY RESTORED in the entire coverage area of ILECO III. Ajuy S/s Time of Interruption: 6:54 PM, March 1, 2024 Feeder 1 – ENERGIZED at 9:52 PM Feeder 2- ENERGIZED at 9:53 PM Sara S/s Time of Interruption: 7:05 PM, March 1, 2024 Feeder 1 – Read more

  • NGCP UNSCHEDULED POWER INTERRUPTION (MARCH 1, 2024 UPDATE as of 11:30 PM)

    With the LIMITED POWER supplied by the National Grid Corporation of the Philippines (NGCP) to the grid, power was restored to the areas catered by the following substations of ILECO III: Ajuy S/s Feeder 1 – ENERGIZED at 9:52 PM Feeder 2- ENERGIZED at 9:53 PM Sara S/s Feeder 1 – ENERGIZED at 11:03 PM Read more

  • NGCP UNSCHEDULED POWER INTERRUPTION (MARCH 1, 2024 UPDATE as of 10:12 PM)

    With the LIMITED POWER supplied by the National Grid Corporation of the Philippines (NGCP) to the grid, power was restored to the areas catered by the following substation of ILECO III: Ajuy S/s Feeder 1 – ENERGIZED at 9:52 PM Feeder 2- ENERGIZED at 9:53 PM The following substations are still UNENERGIZED as of reporting Read more

  • NOTICE TO THE PUBLIC

    Pahibalo sa mga katapo-konsumidores nga ang DISYEMBRE 18, 2023 (LUNES), ang gin-deklara nga SPECIAL PUBLIC HOLIDAY sa ILOILO CITY kag ILOILO PROVINCE, para sa pag-obserba sang “GRACIANO LOPEZ JAENA” base sa Proclamation No. 319 S. 2023. Bangud sini, SARADO ang ILECO III Main Office kaupod ang Area Office (Sara, Natividad) apang BUKAS naman ang Pani-an Read more

  • LIFELINE RATE DISCOUNT

    Read more

  • 12 DAYS TO GO BEFORE CHRISTMAS!

    Read more

  • ILECO III ENERGY SAVING TIPS

    1. Pag-kontrol sang konsumo sang kuryente.2. Pag-gamit sang highly resistive appliances sa tion sang off-peak (kung sa diin barato ang kuryente) ka-angay sang oven, heater, plantsa kag toasters. Likawan ang pag-gamit sang sini nga mga appliances kung peak hours humalin 6:00 PM tubtob 10:00 PM.3. Patyon ang suga sa kwarto kung wala sang tawo.4. Pagsiguro Read more

  • ITB 2501, S. 2025

    Read more

  • ITB 2409, S. 2024

    Invitation to Bid for the Supply and Delivery of kWHr Meters, 5(100) A, Electronic, Single Phase, Bottom Connected (6,434 units) Read more

  • ITB 2408, S. 2024

    Invitation to Bid for the Supply, Delivery and Construction of Distribution Lines and Installation of Kwhr Meter, Service Drop Wires and House Wiring Materials in Three (3) Brgys. (Brgy. Buaya, Brgy. Alipata, and Brgy. San Fernando) in Sicogon Island, Carles, Iloilo (Turn Key) Read more