POWER RATES
POWER ADVISORIES
Ginapahibalo ang tanan nga mga katapo-konsumidores sang ILECO III nga maga-implementar sang ROTATING POWER INTERRUPTION o Manual Load Dropping (MLD), subong nga adlaw alas 7:00 sa aga Enero 3, 2024 ang aton Kooperatiba bangud indi sa gihapon supisyente ang power supply sang mga Power Generation sa Panay Island kag National Grid Corporation of the Philippines Read more
Date: January 02, 2024 (Tuesday) Natividad S/sTime of Interruption: 5:55 PMTime Restored: Feeder 1: 6:55PMFeeder 2: 6:55PMFeeder 3: 2:30 AM Sara S/sTime of Interruption: 5:57 PMTime Restored: Feeder 1 – Not Yet DeterminedFeeder 2 – 9:30 PMFeeder 3 – 9:30 PMFeeder 4 – 9:34 PM Banate S/s Time of Interruption : 5:55 PMTime Restored: Feeder Read more
Date: January 02, 2024 (Tuesday) Natividad S/sTime of Interruption: 5:55 PMTime Restored: Feeder 1: 6:55PMFeeder 2: 6:55PMFeeder 3: Not yet Determined Sara S/sTime of Interruption: 5:57 PMTime Restored: Feeder 1 – Not Yet DeterminedFeeder 2 – 9:30 PMFeeder 3 – 9:30 PMFeeder 4 – 9:34 PM Banate S/s Time of Interruption : 5:55 PMEstimated Time Read more
NEWS AND UPDATES
ILECO III personnel successfully conducted on-site Pre-Membership Seminar (PMS) to 5 recipients of 2023 Sitio Electrification Program (SEP) of Purok 6A, Pangi, San Dionisio, Iloilo on March 12, 2024 (Tuesday). The National Electrification Administration (NEA) appropriated budget to electrify twenty seven (27) sitios with 413 households within ILECO III area coverage for the year. This Read more
ILECO III personnel successfully conducted on-site Pre-Membership Seminar (PMS) to 10 recipients of 2023 Sitio Electrification Program (SEP) of Purok 3A, Madanlog, San Dionisio, Iloilo on March 12, 2024 (Tuesday). The National Electrification Administration (NEA) appropriated budget to electrify twenty seven (27) sitios with 413 households within ILECO III area coverage for the year. This Read more
ILECO III personnel successfully conducted on-site Pre-Membership Seminar (PMS) to 7 recipients of 2023 Sitio Electrification Program (SEP) of Purok 2A, Agdaliran, San Dionisio, Iloilo on March 12, 2024 (Tuesday). The National Electrification Administration (NEA) appropriated budget to electrify twenty seven (27) sitios with 413 households within ILECO III area coverage for the year. This Read more
ILECO III personnel successfully conducted on-site Pre-Membership Seminar (PMS) to 35 recipients of 2023 Sitio Electrification Program (SEP) in Embarcadero, Batad, Iloilo today, March 12, 2024 (Tuesday). The following are the sitios with number of recipients who attended the meeting: Purok Malipayon A, Sta. Ana- 21 Purok 2A, Embarcadero- 11 Purok 3A, Salong- 3 The Read more
BIDS AND NOTICES
Invitation to Bid for the Supply and Delivery of kWHr Meters, 5(100) A, Electronic, Single Phase, Bottom Connected (6,434 units) Read more
Invitation to Bid for the Supply, Delivery and Construction of Distribution Lines and Installation of Kwhr Meter, Service Drop Wires and House Wiring Materials in Three (3) Brgys. (Brgy. Buaya, Brgy. Alipata, and Brgy. San Fernando) in Sicogon Island, Carles, Iloilo (Turn Key) Read more