• UNSCHEDULED POWER INTERRUPTION

    Date: August 08, 2024 Time of power interruption: 6:33 AM Time of restoration: 8:19 AM Affected areas: Bondulan (portion), Poblacion (portion) & Siempreviva (portion), San Dionisio, Iloilo Cause: Line fault due to animal contact For your information. Read more

  • EMERGENCY POWER INTERRUPTION

    Date: August 07, 2024 (Wednesday) Time of power interruption: 9:30 AM Estimated time of power restoration: 12:00 NN Duration: 2 hours and 30 minutes Affected area: Proper, Anoring, Sara, Iloilo Cause of power interruption: Installation of distribution transformer For your information. Read more

  • EMERGENCY POWER INTERRUPTION

    Date: August 05, 2024 (Monday) Time of power interruption: 5:45 PM Estimated time of power restoration: NOT YET DETERMINED Affected areas: Daan Banwa Feeder 3 Municipality of Batad Alapasco, Alinsolong, Banban, Batad Viejo, Binon-an, Bolhog, Bulak Norte, Bulak Sur, Cabagohan, Calangag, Caw-i, Drancalan, Embarcadero, Hamod, Malico, Nangka, Pasayan, Poblacion, Quiazan Florete, Quiazan Lopez, Salong, Santa Read more

  • ILECO III HOTLINE NUMBERS AND PAYMENT CENTERS

    Read more

  • NOTICE TO THE PUBLIC

    Ginapahanumdom ang tanan nga katapo-konsumidores nga sa mga hilikuton kaangay sang Battle of the Sounds, Barangay Fiesta kag pagpatigayon sang welding operations sa mga construction sang puluy-an, buluthu-an kag iban pa nga istruktura nga ginapanugyan gid nga magpatakod sang private ukon kaugalingon nga transformer base sa rekomendasyon sang aton kooperatiba. Ini sandig sa Coop Policy Read more

  • Power Bill kag Rate Composition

    Ka MCO! Aton hibalu-on ang Power Bill kag Rate Composition nga aton makita sa aton Power Bill kada bulan. Diin bala naga-kadto ang aton ginabayaran sa aton kuryente? Matuod gid man bala ang tsismis nga ang isa ka Electric Cooperative ang nagapa-gusto lang sa pag-pasaka sang kuryente? Diri naton mahibaluan kung fixed bala ang Distribution, Read more

  • ANTI-OBSTRUCTION OF POWER LINES ACT (REPUBLIC ACT 11361)

    ‘An Act Ensuring the Continuous and Uninterrupted Transmission and Distribution of Electricity and Protection of the Integrity and Reliability of Power Lines, and Providing Penalties for Violations Thereof.’ Ginadumili-an ang mga masunod: 1. Pagtanom sang maskin ano nga sahi sang matag-as ukon naga-taas nga mga tanom ukon kahoy sa idalom sang distribution lines. 2. Pagpatindog Read more

  • ITB 2201, S. 2022

    15MVA Banate Substation 69KV Structure for Tapping Point and 13.2 kV Double Circuit Distribution Lines (Turn Key Project) Read more

  • ITB 2014, S. 2021

    Procurement of Materials and Equipment for Change Meter/Rehabilitation, ServiceDrop Installation, Housewiring Loan, and Maintenance Use Read more

  • ITB 2012, S. 2021

    Procurement of Boom Truck Read more